Building Progress Reports
By Ed Caulkins
NEW
FACILITY UPDATE - February, 2001
Finally,
we are within a few weeks of worshiping in our new church! It
has been a long and exciting journey. After years of planning
and building, the new worship facility is ready to be occupied.
The
transition begins on Friday, February 16th when the church office
will move into its new home. This is the first step to occupying
the new church. On March 4th, we will hold a transitional service,
which will begin in the current church and finish in our new Sanctuary.
Later that day we will hold our first congregational meeting in
the new church followed by the Lenten Family Night in the new
Family Life Center. This should prove to be a very memorable day
in the life of our congregation.
The
upper floor of the building is almost complete with furniture
already in the rooms. By the end of February, the lower level
of the Education Wing will be complete with furnishings as well.
The last room to be finished will be the kitchen. Due to scheduling
issues, the cooking equipment may not be ready for the Lenten
Family Night but we will have the roasting pans in place to keep
our cooks busy and our stomachs full.
But
first, we have to finish our final construction project - CLEANING.
We would like the congregation to assist in a final house cleaning
party on Saturday, February 24th. A large turnout is essential.
The more people to participate, the shorter the cleaning time.
It is a large building and everyone who comes will make a difference.
Please stop by with your buckets, rags, brooms, vacuum cleaners
and dust rags. We will have soap and cleaning agents available
for your use.
Please
plan to spend part of your day at the new facility to wipe away
that final construction dust and make those windows sparkle. With
everyone's' participation, it will be a fun and painless cleaning
experience. Please remember to mark "Cleaning Saturday", February
24th on your calendar.
NEW
FACILITY UPDATE - January, 2001
The
chandeliers have arrived! On January 8, the long awaited chandeliers
for the Nave and Gathering Space were delivered. They are now
installed and operational. It has been a long wait after several
delays but the final product is now in place. The spotlights in
the Nave have also been aimed. This was not as easy as you might
think considering there are 36 lamps. Mounted up at the underside
of the ceiling, some are as high as 40 feet above the floor.
January
brought dramatic changes on the upper floor. By the end of January,
the following items will be completed:
·
Carpeting in the Nave, Gathering Space, offices and classrooms
· Tile floor in the Gathering Space
· Pews will be installed
· The two smaller stained glass windows
· The organ will be installed
February
will be our final month of construction. The lower level will
be the center of activity as we finish the classrooms, Family
Life Center and kitchen. The drywall is already complete and the
painting in progress. As February continues, the ceilings, lights
and plumbing fixtures on the lower level will be installed.
This
work will bring us to our final project - CLEANING. We would like
the congregation to assist in a final cleaning. It will take a
lot of help to give the building its final cleaning. This will
be split into two times, one for the upper level and another for
the lower level. Stay tuned for further details.
NEW
FACILITY UPDATE - December, 2000
The
masons have completed all the brick and dryvit on the exterior
of the building. A raised cross has been built into the gable
end of the covered drive. If you look close, you will see that
the cross is identical to the processional cross and the cross
that will be mounted on the rear Chancel wall above the granite.
In
the Nave, the painting and oak trim are almost complete. The stained
glass window frames and clear outer protective glass has just
been installed. The organ speakers have been installed in the
front and rear organ chambers. The granite wall is in place, and
the grouting and final trim will be completed next.
The
chandeliers will be installed between Christmas and New Year's
Day. The carpeting will be installed the first week of January,
and the pews will be put in place during the week of January 15th.
Final
site grading is in progress and the parking lot paving and sidewalks
are complete. The base coarse of the parking lot was installed.
The final coarse will be applied next spring.
Work
in the education wing is progressing as the drywall is almost
complete upstairs and the ceramic tile walls and floors in the
restrooms are in place. The church offices are painted and the
ceiling grid and lights installed. The ceiling tiles will be installed
after the computer, telephone and fire alarm wiring is completed.
To
those of you who have been back every Saturday morning to help
clean, thank you for your support.
NEW
FACILITY UPDATE - November, 2000
The month of October supplied us with the driest weather since
construction began. The dry weather has allowed the contractors
to complete the majority of the exterior of the building with
the exception of some doors and the stained glass windows. These
doors will be installed in the near future. The stained glass
windows are still in production at the stained glass studio near
Philadelphia.
The
masons have completed all the brickwork around the Education Wing
and Nave, and are currently working on the columns supporting
the covered drive. They will begin the dryvit work on the west
gable end of the Narthex and the covered drive next.
As
you have all noticed, the steeple was lifted by crane to its'
final location centered over the peak of the Sanctuary roof this
past month. If you think the steeple is leaning to the west, your
eyes are not playing tricks on you. The spire is leaning to the
west approximately 10 inches at the top. This will be remedied
when the winds are calm enough to allow for an adjustment.
In
the Nave, the drywall is now complete. The painters have painted
the front wall and are working on the remaining walls and the
steel connection plates. The base molding and chair rail will
be installed next.
Around
back, the septic system, kitchen grease trap and underground propane
tank have all been installed over the past few weeks. Final site
grading will begin after the parking lot paving and sidewalks
are complete. The base coarse of the parking lot paving is being
installed at this time. The final coarse will be applied next
spring.
Over
the past month, several members have helped to clean the building
on Saturday mornings. It is mostly light work including broom
sweeping and picking up scrap drywall from the floors. It is a
great way to contribute while spending some time reviewing the
construction progress on a weekly basis. Please come and help
between 8:00 AM and 12 noon if you can.
Building
Update - October, 2000
The
building will soon be weather-tight. Exterior walls around the
Sanctuary and Gathering Space are being closed in. Windows have
been installed everywhere but the Sanctuary. The masons have finished
the rear south and east walls of the education wing, and will
continue around the front of the building. In a month, the brickwork
should be complete.
The
installation of the shingle roof is complete over the education
wing, and the Sanctuary roof will be completed in the coming month.
The final insulation and plywood decking are now complete except
for the north side of the Sanctuary.
Nine
of the ten air conditioning units are already in place and the
ductwork is being installed in the lower level. Electrical wiring
in the lower level is almost complete as well. The elevator has
arrived.
The
steeple has been ordered and should arrive in late October. Pew
and altar furniture are now in the production cycle for delivery
after Thanksgiving.
Gift
naming opportunities are still available, such as:
-
Classroom
furnishings $1,000-2,500
-
P.A.
system for Family Life Center $1,200
-
Pews
$2,500 · Altar rail $5,000
-
Outdoor and indoor lighting $10,000 each
-
Carillon $15,000
-
Kneelers $15,000
-
Steeple $25,000
-
Complete classrooms $25,000
-
Kitchen $35,000
-
Nursery $50,000
-
Digital electronic organ $65,000
-
Porte-cochere (covered entrance) $75,000
-
Air-conditioning $150,000
-
Narthex/Gathering Area $150,000
Please
contact the church office if you wish to make a first time contribution
or an additional contribution.
Building
Update - September, 2000
We
have a roof! After several weeks of hard work the roof trusses
and plywood sheathing are finally complete. For those of you who
wonder why it seemed to take so long, here are some facts:
·
172 wood trusses were installed to form the roof of the education
wing.
· 550 sheets of plywood were used to sheath the roof.
· 2000 pounds of nails were used to fasten the trusses in place
and nail the roof decking down.
The
completion of the roof will now allow work inside the building
to progress in spite of the weather. Installation of the shingle
roof will begin very shortly.
The
walls in the lower level are now framed and the electrical work
has begun. Walls around the sanctuary have also begun. The mechanical
contractor will begin his ductwork and air conditioning unit installation
very shortly as well.
Meanwhile,
the masons will begin laying the exterior brick. This work will
take approximately 8 weeks and use more than 96,000 bricks. The
exterior windows and doors will be installed after the remainder
of the exterior walls are framed and sheathed.
We
are still striving to be in the new sanctuary for Christmas. Keep
the weather in your prayers. Every bit helps!
Building
Update - August, 2000
If
you've been by the new facility recently, the progress there speaks
for itself. The concrete slab under the sanctuary floor is almost
complete. Masonry walls are being finished, and soon we will see
more structure rise around the Education wing.
A
new feature has been added to our church. Our contractor raised
a concern that the future bell tower may create a long term waterproofing
problem. Since we could not solve the problem to the entire committee's
satisfaction, a change has been made. The bell tower will not
be built. Instead, a steeple will be installed directly over the
Sanctuary.
The
steeple will be forty-five feet high with a cross at the pinnacle.
Lighting will accent the steeple at night as it will tower eighty-five
feet above the ground. With this new addition, we believe the
new building will clearly identify itself as a church.
The
installation of this steeple required some additional framing
members in the roof structure. On July 11, Pastor Moore and Rolland
Snyder rented a truck and left for Sydney, NY at 5:30 a.m. Just
after lunch, they returned with framing required to complete the
sanctuary roof and provide the support for the new steeple. The
steeple itself will be installed later this fall.
Building
Update - July, 2000
What
a difference a month makes - now you can really see what the new
facility will be like. The Sanctuary arches are set in place and
the roof deck installation is in progress. If you walk under the
roof, you can look up to see the finished wood, and begin to get
a feel for our new worship area. The back wall of the education
wing is also progressing, and the first floor steel and decking
are in place. The concrete deck for the first floor will be poured
shortly. After this, the outside masonry walls of the education
wing can be built and roof trusses over the classrooms will complete
the outer shell.
Site
grading will be finished around the building and behind the storm
detention pond. The lower parking area will be graded and covered
with stone, in preparation for paving later in the year.
Electrical,
plumbing and air conditioning systems are progressing as well.
The incoming electric service is almost complete and the underground
conduit in place. Plumbing is complete below the lower level floor
slab and the water line has been terminated inside the building.
Ductwork, electrical, and plumbing is being installed below the
sanctuary floor slab.
We
are working on the interior decorating schemes for the education
wing and family life center. If you have an interest in this area,
please attend a Furnishings and Interior Decorating committee
meeting on Monday, July 17 at 7:00 PM in the narthex, or talk
to Marion Greenwood or Keith Grim to join the committee.
Building
Update - June, 2000
Steel
for the education wing and the wood arches for the sanctuary have
finally arrived. The building is finally taking shape and rising
above the foundation walls. From here on, the progress will be
much more noticeable while passing by.
Daryl
Geiger, a member of our congregation and a cabinet maker, has
volunteered to construct the office furnishings for the new facility.
The kitchen layout is complete, equipment from Weis/King's has
been cleaned, and a small freezer and commercial refrigerator
has been offered to the congregation. Both the Celebration and
Decorations Committees are preparing for their role in the new
facility.
Over
the past year and a half, we have attempted to keep you informed
about the building design and construction progress through newsletter
articles, council notes and Temple Talks. The purpose of this
article is to bring you up to date on some of the decisions that
have been made and on some issues still pending.
Approximately
one year ago, (April '99 and May '99 newsletters) the Building
Construction Committee recommended that the entire facility be
constructed at one time, rather than phasing, even though some
parts of the interior might not be finished until later. One month
later, Council recommended that the Building Committee pursue
a less ambitious plan than originally designed in order to keep
costs down. In January 2000, the base building cost took an abrupt
leap of approximately $300,000. This rise in cost was brought
about in large part due to stricter building codes.
Now
the good news! Through some innovative design changes, often prompted
by suggestions from our contractor Harold Blacker, and the tremendous
outpouring of financial support from members and friends of the
congregation, we are on target to have a facility that will have
17 classrooms, a sanctuary that will seat 575+, and a Family Life
Center that is back to its original size. The sanctuary will have
a state-of-the-art organ, beautiful stained glass windows and
top quality furnishings. Through the generosity of Weis/Kings,
our kitchen will be complete as well. Although the Building Committee
is working to keep costs well within the limits of the mortgage
arrangements as approved by the congregation, finishing all the
classrooms and erecting the bell tower still remain as somewhat
wishful options. Within a short time, a decision to delay or build
the bell tower will have to be made; decisions on the classrooms
can be delayed a bit longer. These decisions, frankly, will become
financial decisions.
With
sufficient additional funds or pledges, we can move into a completely
finished and furnished facility. If you wish to make a first time
gift or an additional gift to the building fund, please contact
the church office. There are also several naming opportunities
still available. More information can be obtained by contacting
the church office or the Building Construction Committee.
Finally,
many thanks for the tremendous support you have given. Your gifts
exemplify the meaning of Christian stewardship.
Building
Update - May, 2000
With
the coming of spring, the pace of construction is picking up.
The foundation walls for the Sanctuary are almost complete. If
you walk around the site, you will notice the configuration of
the new Sanctuary is much different from our current facility.
The new Sanctuary is much wider and shallower. This will bring
everyone closer to the Chancel.
In
mid-May, the large arches will arrive. When these arches are set
in place, they will reach 40 feet at the peak. At that time, the
Sanctuary will finally begin to take form and become visible from
the road.
The
east end of the parking lot has been graded and covered with stone.
This will serve as a staging and storage area for the brick delivery
at the end of April. The brick delivery will require ten flatbed
tractor-trailers.
The
storm drainage work is almost complete. The storm water catch
basins and piping from the parking lots to the retention pond
are all in place. When the paving is complete, all the rainwater
from the parking lots will be directed to the storm detention
pond at the rear of the building.
In
March, Weis/King's donated table service and kitchenware from
their closed restaurant in Hamburg. On April 1, volunteers moved
additional kitchen equipment from Hamburg to local storage. Weis/King's
sold us this equipment, which included stove, range top, griddles,
fryers, stainless steel worktables, dishwasher, steam table, sandwich
bar, and more. All this equipment was received for $4000, a fraction
of the cost if purchased new. Items that we do not need will be
sold, and the money used to offset other kitchen costs. We have
sent Weis/King's a thank-you letter for their generous support
on behalf of the entire congregation.
The
interior decorating schemes for the Sanctuary and offices are
complete. We will be continuing with interior finishes of the
Education Wing next. A model and finish board will be on display
in the near future.
As
you can see, work is moving quickly in many areas of this project.
Just as the three crosses rose out of the hill on our site during
Lent, the upcoming months will feature many facets of our new
Worship Facility rising from the ground up.
Building
Update - April, 2000
Work
is progressing rapidly on our new facility, with the cooperation
of good weather. Concrete work continues as building footers and
foundation walls are formed and poured. Here are some facts:
-
As
of March 17, we have poured 424 cubic yards of concrete, the
equivalent of 42 cement truckloads. A total of 1042 cubic yards
will be poured before we are done, the equivalent of 101 cement
truckloads.
-
The
concrete basement walls of the education wing are complete except
the back wall, which will be block and brick.
-
Foundations
for the Sanctuary are under way.
-
The
curbing in the parking area has been started and will be completed
after the Building is under roof.
Site
drainage work will resume over the next few weeks. Wessner Excavating
will install the storm water catch basins and piping from the
parking lots to the storm water retention pond. You may have already
noticed the large pile of piping and concrete catch basins along
Washington Street.
The
plumbers will install the water line into the building in the
next few weeks.
Work
is progressing inside the building as well. The pews and Chancel
furniture have been finalized and will be ordered this week. The
interior decorating schemes for the Sanctuary and Offices are
almost complete. We will be continuing with interior finishes
of the Education Wing next.
Weis/King's
has donated flatware, dishes, pots, pans, glasses, trays and other
kitchen items too numerous to list. All these items are from the
Hamburg Store Restaurant, which closed at the end of 1999. Thanks
to Judy Gifford, Curtis Schneck, and others, who all had a part
in obtaining these items.
Thanks
also to David and Ruth Schneck for providing storage space, and
to the volunteers who helped move all these items from Hamburg
into storage. In addition, we are negotiating to purchase some
of Weis/King's kitchen appliances at a reduced price. This will
provide a real savings to our original budget.
Building
Update - March, 2000
This
month, the Building Construction committee would like to share
with you a list of "Did You Know Facts" about our new facility:
-
The
new facility will use 96,105 bricks for the exterior walls.
-
The
roof and walls will require 1006 sheets of plywood.
-
The
building will have ten separate heating and air conditioning
systems.
-
The
parking lot will hold 187 cars and require 10,566 square yards
of blacktop.
Outdoor
construction work has been slow over the past month due to Mother
Nature. The organ for the new Sanctuary has been ordered. The
pew and chancel furniture are being finalized by the Building
and Worship & Music committees in conjunction with the interior
decorator from Spillman Farmer and the pew manufacturer. The design
of the kitchen is being considered, and the Education committee
is reviewing the needs for classroom furniture.
Many
items must be examined and decided over the course of the next
several months. Please let us know if you can participate in any
of the following task groups:
-
Furnishings
and interior decorating
-
Memorials
and special gifts
-
Education
planning and programming
-
Sound
equipment, telephone, data, acoustics
-
Kitchen
equipment and layout
-
Celebration
and events (Open House and Dedication)
You
all have the opportunity to participate in this once-in-a-lifetime
experience of building a new church. If you have an interest in
any of the topics above, please call the church office so we can
contact you with the dates and times we will be meeting. As always,
if you have any questions, please do not hesitate to contact a
member of the Building Committee or the church office.
Building
Update - February, 2000
If you have time, stop at the site and see what is happening.
We think you will be excited to stand in the middle of our future.
Work is progressing in spite of the variable weather conditions,
and becoming more visible each week.
Foundation
walls for the Education Wing continue to be formed and poured,
as the weather allows between rain and cold. The remainder of
the Education Wing walls will be formed and poured before the
work on the Sanctuary foundation begins.
As
you visit the site, the concrete walls you see are the front of
the Education Wing, lower level. These walls will serve as a retaining
wall when the ground is pushed back up against them. By looking
at the wall height, you can begin to get a sense of how high the
church will sit on the site.
The
lower level of the Education Wing will open onto grade at the
back, similar to a walkout or open basement in a house. Upon the
completion of the lower level walls, the steel framing for the
upper level floor will be built, followed by the upper level walls
and roof. The structural steel for the Education Wing will be
manufactured soon.
The
bricks for the exterior of the building have been ordered. The
wood arches for the Sanctuary are scheduled for delivery in mid
March. These arches will be 40 feet tall at the peak.
The
Building Committee and the Music & Worship Committee are working
on pew and Chancel furniture details.
We
will continue to keep you updated on a monthly basis in the newsletter
and at one Sunday Worship service each month. If you have any
questions please do not hesitate to contact the Building Committee
or Church Office.
Building
Update - January, 2000
Work
is still progressing on the site, though it is hard to see from
the road. The only visible item is the straw and seed on the topsoil
stock pile. This seeding will stabilize the pile, and was required
by the Lehigh County Conservation District. The parking lot grading
is also finished, in preparation for stone.
The
rest of the work is below the surface. The basement excavation
is complete. Building footers and foundation walls are being formed
and poured as weather allows between rain days. As of mid-December,
75 cubic yards of concrete have been poured. A total of 1042 cubic
yards will be poured to complete the job, which is the equivalent
of 101 cement truck loads.
38,000
pounds of steel reinforcing bars have been delivered to the site
to be installed in the footers and foundation walls. An additional
38,000 pounds is required to complete the concrete work.
The
manufacturer for the laminated arches which will form the new
Sanctuary is developing shop drawings. Sample bricks were assembled
into mock up walls for final selection. The Building Committee
continues to evaluate pew and organ proposals for the new Sanctuary.
|